//! Resource and time conflict detection.
//!
//! A schedule can be wrong in several ways, and this crate finds them. It
//! reports conflicts rather than refusing them, so that a plan loaded from a
//! file can be checked in full and every problem listed at once instead of
//! one per attempt.
//!
//! Five kinds of conflict are detected:
//!
//! - **Capacity**: two placements need more of a resource at the same instant
//! than the resource has.
//! - **Window**: a placement starts before its task may, or ends after it
//! must.
//! - **Requirement**: a placement's task is not known, or its duration does
//! not match the schedule.
//! - **Availability**: a placement falls outside the availability windows of
//! a resource it needs, so the resource would not actually be there.
//! - **Precedence**: a task that must follow another starts before it ends.
//!
//! The distinction between a capacity conflict and an availability conflict
//! matters in practice: the first says the plan is over committed, the second
//! says the plan asks for a resource at a time when it is switched off or out
//! of view, which is a different repair.
//!
//! ```
//! use apsis_resource::{Resource, ResourceId, ResourceSet, Window};
//! use apsis_schedule::Schedule;
//! use apsis_task::{Task, TaskId};
//! use apsis_conflict::{ConflictKind, detect};
//!
//! let mut station = Resource::new(ResourceId::new(0), 1.0);
//! station.set_windows(&[Window::new(0.0, 1_000.0)]).expect("usable");
//! let resources = ResourceSet::from_resources(vec![station]).expect("distinct");
//!
//! let task = Task::new(TaskId::new(0), 60.0)
//! .try_require(ResourceId::new(0), 1.0)
//! .expect("the resource is new");
//! let mut schedule = Schedule::new();
//! schedule.place(&task, 100.0).expect("the task fits");
//!
//! let report = detect(&schedule, &[task], &resources);
//! assert!(report.is_clear());
//! assert_eq!(report.conflicts().len(), 0);
//! let _ = ConflictKind::Capacity;
//! ```
//!
//! 资源与时间冲突检测。
//!
//! 一份调度可能以若干方式出错,本 crate 找出它们。它报告冲突而非拒绝它们,使从
//! 文件加载的计划能被完整检查,并一次列出每个问题,而不是每次尝试报一个。
//!
//! 检测五类冲突:
//!
//! - **容量**:两处放置在同一瞬时需要的某资源超过该资源所有。
//! - **窗口**:一处放置在任务可开始之前开始,或在它必须结束之后结束。
//! - **需求**:一处放置的任务未知,或其时长与调度不符。
//! - **可用性**:一处放置落在它所需某资源的可用性窗口之外,故该资源实际上不在场。
//! - **先后**:一个必须跟随另一任务的任务在其结束之前开始。
//!
//! 容量冲突与可用性冲突之别在实践中要紧:前者说明计划超额承诺,后者说明计划在资源
//! 被关闭或不可见之时索求它,二者是不同的修复。
#![forbid(unsafe_code)]
#![deny(missing_docs)]
mod conflict;
mod detect;
pub use conflict::{Conflict, ConflictKind, ConflictReport};
pub use detect::{Precedence, detect, detect_precedence, placements_of};
pub use apsis_resource::{ResourceId, ResourceSet};
pub use apsis_schedule::Schedule;
pub use apsis_task::{Task, TaskId};